Market data

Structure data

Want to find out the circuit length, geographical area of the grid territory or average interruption time? Here you can find all the important structure data.

Network facts and figures

EnWGEHV S EHV/HV
§ 23c (1) Nr. 1: Circuit length of overhead lines (km)3.098 1,0
§ 23c (1) Nr. 1: Circuit length of cables (km)3 9,0
§ 23c (1) Nr. 2: Installed capacity at substation level (MVA)5.870 21.030
§ 23c (1) Nr. 3: Annual energy used by customers (GWh)1.199 35.726
§ 23c (1) Nr. 4: Connection points99 85
§ 23c (1) Nr. 5: Number of inhabitants in the grid area approx. 11 million 
§ 23c (1) Nr. 6/7: Served area/Size of control area (km2) 34.600 
§ 23c (1) Nr. 8: Number of sampling points with a power measurement every fifteen minutes or a meter reading 102 
§ 23c (1) Nr. 9: Responsible measuring point operator TransnetBW GmbH 
§ 23c (1) Nr. 10: Contact for grid access Contact 
EnWGEHV S EHV/HV
§ 23c (1) Nr. 1: Circuit length of overhead lines (km)3.100 1,0
§ 23c (1) Nr. 1: Circuit length of cables (km)4,0 9,0
§ 23c (1) Nr. 2: Installed capacity at substation level (MVA)5.870 21.030
§ 23c (1) Nr. 3: Annual energy used by customers (GWh)960 37.846
§ 23c (1) Nr. 4: Connection points17 84
§ 23c (1) Nr. 6/7: Served area/Size of control area (km2) 34.600 
§ 23c (1) Nr. 8: Number of sampling points with a power measurement every fifteen minutes or a meter reading 101 
§ 23c (1) Nr. 9: Responsible measuring point operator TransnetBW GmbH 
§ 23c (1) Nr. 10: Contact for grid access Contact 
StromNEVEHV S EHV/HV
§ 27 Abs. 2 Nr. 1: Circuit length of overhead lines (km)3.154 1,0
§ 27 Abs. 2 Nr. 1: Circuit length of cables (km)4,0 9,0
§ 27 Abs. 2 Nr. 2: Installed capacity at substation level (MVA)5.570 20.980
§ 27 Abs. 2 Nr. 3: Annual energy used by customers (GWh)1.029 36.433
§ 27 Abs. 2 Nr. 4: Connection points18 85
§ 27 Abs. 2 Nr. 7: Size of control area (km2) 34.600 
§ 27 Abs. 2 Nr. 8: Number of sampling points with a power measurement every fifteen minutes or a meter reading 103 
§ 27 Abs. 2 Nr. 9: Responsible measuring point operator TransnetBW GmbH 
StromNEVEHV S EHV/HV
§ 27 Abs. 2 Nr. 1: Circuit length of overhead lines (km)3.153 1,0
§ 27 Abs. 2 Nr. 1: Circuit length of cables (km)3,0 8,0
§ 27 Abs. 2 Nr. 2: Installed capacity at substation level (MVA)5.570 21.110
§ 27 Abs. 2 Nr. 3: Annual energy used by customers (GWh)1.149 38.658
§ 27 Abs. 2 Nr. 4: Connection points18 84
§ 27 Abs. 2 Nr. 7: Size of control area (km2) 34.600 
§ 27 Abs. 2 Nr. 8: Number of sampling points with a power measurement every fifteen minutes or a meter reading 102 
§ 27 Abs. 2 Nr. 9: Responsible measuring point operator TransnetBW GmbH 
StromNEVEHV S EHV/HV
§ 27 Abs. 2 Nr. 1: Circuit length of overhead lines (km)3.184 1,0
§ 27 Abs. 2 Nr. 1: Circuit length of cables (km)3,0 8,0
§ 27 Abs. 2 Nr. 2: Installed capacity at substation level (MVA)5.570 20.610
§ 27 Abs. 2 Nr. 3: Annual energy used by customers (GWh)1.321 41.217
§ 27 Abs. 2 Nr. 4: Connection points19 85
§ 27 Abs. 2 Nr. 7: Size of control area (km2) 34.600 
§ 27 Abs. 2 Nr. 8: Number of sampling points with a power measurement every fifteen minutes or a meter reading 104 
§ 27 Abs. 2 Nr. 9: Responsible measuring point operator TransnetBW GmbH 
 EHVS EHV/HV
Annual energy used by customers (GWh)1.25742.078
Circuit length of overhead lines (km)3.1870,9
Circuit length of cables (km)3,27,1
Installed capacity at substation level (MVA)5.57020.630
Connection points1885
Size of control area (km2)34.600 

Legend

EHV: Extra high voltage, S: Substations, HV: High voltage, GWh: Gigawatt hours, MVA: Megavolt amperes

Grid losses

StromNEV (EnWG)EHV S EHV/HV
§ 10 (2) (§ 23c (2) Nr. 3): Annual energy (GWh) 967 
§ 10 (2): Grid losses (%)2,3 0,3
§ 10 (2) (§ 23c (2) Nr. 7): Average procurement costs (€ct / kWh) 8,4 
StromNEV (EnWG)EHV S EHV/HV
§ 10 (2) (§ 23c (2) Nr. 3): Annual energy (GWh) 803 
§ 10 (2): Grid losses (%)1,8 0,3
§ 10 (2) (§ 23c (2) Nr. 7): Average procurement costs (€ct / kWh)  3,9 
StromNEVEHV S EHV/HV
Annual energy (GWh) 658 
§ 10 Abs. 2: Grid losses (%)1,5 0,3
§ 10 Abs. 2: Average procurement costs (€ct / kWh)  5.3 
StromNEVEHV S EHV/HV
Annual energy (GWh) 686 
§ 10 Abs. 2: Grid losses (%)1,4 0,3
§ 10 Abs. 2: Average procurement costs (€ct / kWh)  3,5 
StromNEVEHV S EHV/HV
Annual energy (GWh) 780 
§ 10 Abs. 2: Grid losses (%)1,5 0,3
§ 10 Abs. 2: Average procurement costs (€ct / kWh)  2,8 
 EHVSEHV/HV
Grid losses (%)1,7 0,3
Annual energy (GWh) 862 
Average procurement costs (€ct / kWh) 2,8 

Average Interruption Time (AIT)

EENS-SI [MWh]YEC [TWh]AIT
0370min 0sec
EENS-SI [MWh]YEC [TWh]AIT
0390min 0sec
EENS-SI [MWh]YEC [TWh]AIT
0370min 0sec
EENS-SI [MWh]YEC [TWh]AIT
0400min 0sec
EENS-SI [MWh]YEC [TWh]AIT
0430min 0sec
EENS-SI [MWh]YEC [TWh]AIT
0430min 0sec
EENS-SI [MWh]YEC [TWh]AIT
0440min 0sec
EENS-SI [MWh]YEC [TWh]AIT
0440min 0sec
EENS-SI [MWh]YEC [TWh]AIT
0440min 0sec
EENS-SI [MWh]YEC [TWh]AIT
187462min 8sec
EENS-SI [MWh]YEC [TWh]AIT
0470min 0sec
EENS-SI [MWh]YEC [TWh]AIT
0500min 0sec
EENS-SI [MWh]YEC [TWh]AIT
0510min 0sec
EENS-SI [MWh]YEC [TWh]AIT
0520min 0sec
EENS-SI [MWh]YEC [TWh]AIT
229522min 20sec
EENS-SI [MWh]YEC [TWh]AIT
0520min 0sec

Legend

  1. EENS-SI

    „Estimated Energy Not Supplied for each Sustained Interruption“ 

  2. YEC

    „Yearly Energy Consumption“ 

  3. AIT

    „Average Interruption Time“