ANCILLARY SERVICES

Non-frequency-related ancillary services

BACKGROUND AND PROCUREMENT

Inertia

Frequency deviations can occur in the event of imbalances between the electrical energy supplied and that consumed in a given area. These deviations can occur almost immediately and, depending on the cause, at different locations, for example in the event of a system split. With such rapid changes, inertia is required to immediately and effectively cushion rapidly occurring power imbalances until the primary control system stabilises the grid frequency and secondary control restores it to 50 Hz.

At present, the available inertia is mainly determined by the number and size of the available synchronous generators. In the course of the energy transition, however, these capacities will decrease and power generation based on renewables and battery systems will increase. These latter resources will increasingly have to provide the ability to provide inertia electronically in order to meet demand.

In order to support this development and ensure that sufficient plants capable of providing inertia will be available to ensure stable grid operation in the future, TransnetBW will soon initiate market-based procurement of inertia on the basis of Section 12(h) of the Energy Industry Act (EnWG).

The Federal Network Agency has initiated a procedure under file number BK6-23-010 to define the specifications and technical requirements for the future market-based procurement of inertia. TransnetBW is actively supporting this process and will implement the appropriate procurement processes once the new framework conditions have been defined by the Federal Network Agency.

BACKGROUND AND PROCUREMENT

Black start capability

As the transmission system operator responsible for the control area, TransnetBW maintains restoration and recovery plans to restart parts of the power grid in case of a blackout. These plans describe how the transmission system can be gradually restored to power after a large-scale power outage. This requires power generators that can generate power without an external supply of power and thereby restore power to sub-grids.

With resolutions BK6-21-023 and BK6-18-249, the Federal Network Agency specified framework conditions for the transmission system operators' procurement procedures for contracting these black start system services.

Tender

TransnetBW is currently planning two tenders with the aim of contractually securing the necessary black start capability in future: A first tender is planned in January 2024 for the TransnetBW West region, another tender in June 2025 for the TransnetBW East region.

  1. Information on tender participation can be found here:

An overview of the tenders planned throughout Germany and further information can be found under "Marktgestützte Beschaffung Schwarzstartfähigkeit" at netztransparenz.de.

As the transmission system operator responsible for the control area, TransnetBW maintains restoration and recovery plans to restart parts of the power grid in case of a blackout. These plans describe how the transmission system can be gradually restored to power after a large-scale power outage. This requires power generators that can generate power without an external supply of power and thereby restore power to sub-grids.

With resolutions BK6-21-023 and BK6-18-249, the Federal Network Agency specified framework conditions for the transmission system operators' procurement procedures for contracting these black start system services.

BACKGROUND AND PROCUREMENT

Reactive power

In order to ensure the undisturbed flow of electricity in the grid, TransnetBW must ensure a constant voltage in its network. This requires, among other things, the use of reactive power. This reactive power is provided by network components such as coils (inductors) and capacitor banks (further information about reactive power in general and TransnetBW activities in particular is portrayed (only in German) here: STATCOM-Anlagen - Innovation - Porträt - Unternehmen - TransnetBW), and from third-party systems such as power plant generators, power converters or battery storage systems.

The Federal Network Agency has initiated a procedure under BK6-23-072 in order to establish rules and technical requirements for the future market procurement of reactive power. TransnetBW is actively supporting the process and will implement the corresponding procurement procedures once the new framework conditions have been finally set by the Federal Network Agency.